Question (5/50)

Ten women can complete a work in 7 days and ten children take 14 days to complete the same work. How many days will 5 women and 10 childeren take to complete the same work ?

(A)  3 Days


(B)  5 Days


(C)  7 Days


(D)  9 Days


Premium Register as premium memeber to know answer & explanation. Only INR 10/Month.

Question (6/50)

Twelve men can complete a piece of work in 4 days, while fifteen women can complete the same work in 4 days. Six men start working on the job and after 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days ?

(A)  15


(B)  18


(C)  20


(D)  22


Premium Register as premium memeber to know answer & explanation. Only INR 10/Month.